A saved program does not make a coil change invisible to production. Diameter, delivered condition, surface and coil behavior may differ. A wire coil change checklist connects the last accepted sample to the first output from the new supply.
Retain the previous lot identification and a measured accepted part. Record program revision, tooling and approved settings. A sample marked good without measurements offers less diagnostic value than a traceable record of its critical dimensions.
Match grade, nominal size, delivered condition and lot to the production order and material documents. Inspect accessible wire for damage, corrosion and contamination. Measure diameter at suitable locations and orientations with an appropriate instrument.
Record coil shape and handling damage that could affect feeding. Load and thread under the machine-specific procedure, controlling stored energy and the free wire end. A material certificate supports traceability but does not replace examination of the actual coil.
Confirm the payoff arrangement, guide route and straightening setup against the recorded condition. Inspect for loose guides, debris and roller damage under safe isolation. Once operation resumes, observe protected feeding for irregular unwinding or intermittent tension.
Do not immediately alter bend compensation because the first sample differs. First establish that the correct program and tooling are installed and that feeding is consistent. Otherwise a correction may hide a loading error and create a different problem later in the coil.
Identify the new first part and inspect drawing-critical features from the same datums used for the retained sample. Include lengths, angles, out-of-plane geometry and surface condition as applicable. Preserve the first-off result even if later parts pass.
Inspect consecutive samples and a defined restart using the agreed sampling plan. One good part proves only that one part passed. Record production order and whether dimensions settle, drift or scatter. Select sample counts according to the quality plan rather than adopting a universal number.
If the shift follows a new lot, compare actual material information before concluding that machine accuracy has changed. If the issue follows rethreading, investigate setup references. Record every approved adjustment with its reason, previous value, new value and verification. Keep startup parts identified until disposition. Send Jinchun Machine the drawing, coil details and before-and-after records when requesting support.
Review feed-system behavior when new coils unwind inconsistently. See wire payoff systems guide.
Use this related article for angle changes remaining after setup checks. See springback control in CNC bending.
Review corresponding equipment with the coil and part requirements. See industrial CNC wire bending machine.